Production Order could be split due to following reasons:
- When partial lot of order is to be handled from the rest due to quality reasons.
 - If capacity bottle necks exists.
 - Material is committed for part of order qty.
 
Features:
- The split operations and the material assigned are copied into the child order.
 - The structure of the parent order does not changes while the split off operations are copied into the child order
 
Status for parent order : SPLT
Status for the child order: SPLE
For operation : SPLT
Restrictions:
- The parent order and the child order must be settled to same cost collector
 - Read PP Master data is not possible
 - Confirmations at header level is not possible
 
Steps to perform split:
- In OPL8 Set the indicator cost collector
 - Default Rule -Periodic settlement(PP2)
 - CK11N do standard cost estimate
 - KKF6N Create cost collector
 - Create production order with op10,20,30,40
 - Go to op overview
 - Select the op from which you want to split (exop20)
 - Go to functions ----> Split order
 - Enter the qty ,if necessary a different order type for the child order
 - Execute
 - Order will be splitted .
 - The order can be splitted even from op10 itself
 - Goto MD04
 - Two orders will be created
 - Go to op overview of each order and there you can see the splitting.
 