Q: Can we use same routing for materials undergoing the same process/operations? Can we avoid separate routing for each and every material produced?
A1: Presume that there are 50 products and the fabrication shop uses a set of 10 machines. If all these products use the same settings of the machines, Reference Operation Sets (task list type S) can be setup for common processes that use the same work centers. However costing, scheduling and capacity will be affected if each product has different setup time and Reference Operation sets can not be used.
A routing for each material number ( type N or R) has to be set up and within that routing, the Reference Operation Set can be used.
However you can by try utilizing the KMAT material and product variants invariant configuration to avoid separate routing for each material.
A2: You may create a routing group. Go into routing creation and enter the plant and the group name. If you want you may name the group , else name is assigned by internal counter). Create the routing with the work centers, operation times, etc. Go to the "Header overview" screen and click on the "Mat Alloc" screen. Fill in the blanks with all the material masters that use this routing.
How to Earn Rs.25000 every month in internet without Investment?
Friday, November 30, 2007
Routing
Subscribe to:
Post Comments (Atom)
Blog Archive
-
▼
2007
(138)
-
▼
November
(124)
- Possible Combinations of Configuration Profiles
- Changing/Displaying/Deleting Configuration Profiles
- Interface Settings
- Multi-Level BOM Explosion
- Single-Level BOM Explosion
- Controlling the BOM Explosion in PP
- Process: Order BOM
- Process: Sales Order
- Process Overview
- Availability of Components
- Filters for BOM Explosion
- Class Assignment
- Creating a Configuration Profile
- The Configuration Profile
- Defining Classes as BOM Items
- Variant Classes
- Reporting: Characteristics and Values
- Maintaining Characteristics for Configuration
- Routings for Configurable Materials
- Finding Objects in a Class Item
- Selection from a Class Item: Example
- Selection from a Class Item
- Classification as a Selection Condition
- Selecting BOM Items
- Super BOM
- Material Master Data for Configurable Materials
- Defining a Material as Configurable
- Variant Configuration (LO-VC)
- variable size
- Production Orders
- Production Orders
- Production Orders
- Production Orders
- Production Orders
- Production Orders
- Production Orders
- Production Orders
- Production Orders
- M R P
- M R P
- M R P
- M R P
- Demand Management
- Sales & Operations Planning
- Routing
- Routing
- Routing
- Work Centers
- Bills Of Material
- PP Faqs
- Free download sap PP Books
- Transactions
- All Tables
- Production Planning Tables
- Books
- Subcontracting In SAP in PP
- Collective Confirmations in Repeatitive Manufactur...
- What Transaction to Perform Discontinued Parts in PP
- Inspection Characteristics Indicator in the Contro...
- Scrap Management in Finished Product in PP
- Meaning of Costing Variant in SAP PP
- Same serial number assigned to several production ...
- Question : Subject : Basic dates history in produc...
- Mass Processing for Production Order in PP
- Change Production Order - CO02 in PP
- Production Order Status in PP
- Control whether the Production Order operations wi...
- Control parameters for production order conversion...
- Print Shop Papers - Configure new / existing SAP P...
- COGI - Keep track of all the back flushing failure...
- Search for Open Production Order in PP
- Configure a New Production Order Type in PP
- Sample ABAP on Multi-Level Bom with Location Balance
- Writing a Multi-Level BOM Cost Roll-up with ABAP
- Determine whether Planned / Production Order are i...
- Difference Between Planned & Prod. Orders in PP
- Firmed Planned Orders, What is its use in Producti...
- Mass Delete Planned Order in PP
- Production Operations Overlapping in PP
- CA03 - Display Routing in PP
- Attach The Components Drawing In a BOM in PP
- Long Term Planning BOM Selection in PP
- To compare multiple BOMs in PP
- Total Plan Activities in Minutes in PP
- Configuring an Additional Activity Type in PP
- Work Center Creation and Change in PP
- The Concept (use) of Phantom Assembly in PP
- Configure Phantom assembly in PP
- BOM Display Changes in PP
- BOM components never explode
- SAP SOP - Sales, Operation and Planning (Info Stru...
- SAP MRP Profile - How To Used It
- Problem in the MRP Run and Frequency in PP
- MRP Run Exception Description in PP
- Individual Collective Indicator in the MRP 4 View ...
- Processing Keys NETCH & NETPL in MRP in PP
- How System choose Production Version in PP
- Question : Subject: MRP, timing of purchase reques...
- Connecting the planning calendar to your lot size ...
- Mass change MRP indicator in PP
-
▼
November
(124)
No comments:
Post a Comment