Q: Can we have more than 6 standard values in standard value key?
A: One way to achieve this is to create another operation step using the same work center. However this shall be with a control key that is not a milestone. When the milestone operation is confirmed, the previous operations up to the next milestone are automatically confirmed. To get the desired number of standard values , all the 'non milestone' steps can be built depending on the need.