Routing

Q: Scheduling times can be defined in the material master record by;
# entering the in-house production time. This value can be updated from the routing by the system.
# entering the setup, tear down, processing, and interoperation times. If these values are maintained, the system determines the in-house production time on the basis of lot size.
How do you get the system to update this value from the routing?
A: In routing, carry out scheduling. Go into the routing operation overview and follow Extras -> Scheduling -> Results. The pop-up window displays the scheduling data. At the bottom there is a pushbutton to copy the scheduling data to the material master Check this push button to update master data.